Project Profile | Rio Tinto Oita

CLIENT
Rio Tinto

VESSEL
Pilbara Iron Co – Oita

PROJECT OBJECTIVE
Delivering major survey compliance and enhancing fleet performance through integrated marine maintenance.

PROJECT STATUS
Complete – June 2025

About the Project

SeaReady was engaged by Rio Tinto to complete a comprehensive dry docking and refit of Oita, a 33-metre ASD tug operating in Dampier as part of the Rio Tinto towage and line boat fleet. Built in 2010, Oita is a Robert Allan-designed RAmpart 32 vessel powered by twin Niigata main engines and capable of delivering 65 tonnes of bollard pull.

The project focused on achieving Oita‘s 15-year class survey while extending vessel longevity, improving operational efficiency, and optimising hull and engine performance. SeaReady was selected for its proven capability, strong project management, and long-standing relationship with the Rio Tinto fleet.

Project Details
Scope of Works

Hull & Structural

  • Removal and refit of fenders
  • Full surface preservation

Machinery & Propulsion

  • Overhaul of Niigata ZP41 azimuth thrusters
  • Removal of port and starboard forward winches to replace main shaft bearings

Tank & Void Maintenance

  • Cleaned fresh water ballast and domestic tanks
  • Replaced AFFF firefighting foam
  • Calibrated and tested tank sensors

Hydraulics & Piping

  • Overhauled hydraulic motors on anchor and chain systems
  • Removed and replaced 16 vessel valves
  • Opened and ultrasonically cleaned coolers

Dry Docking & General Services

  • Supplied crane services, elevated work platforms, forklifts, and cherry pickers
  • Supplied and installed vessel signage
  • Provided emergency response team (ERT) services for confined space works

Electrical Systems

  • Completed full electrical survey in line with LRS class requirements
  • Overhauled AC generators
  • Conducted megger testing of all electric motors
  • Inspected main mast navigation lighting for extended service

Supplementary Works

  • Removed and replaced wheelhouse windows
  • Cropped and replaced starboard main engine exhaust hanger mounts

Challenge

Contractor Coordination

AFFF Disposal Compliance

SeaReady’s Response

  • Developed a unified project schedule integrating all contractor timelines and dependencies. Daily site meetings ensured sequencing alignment and proactive issue resolution.
  • Engaged certified waste disposal providers. Implemented safe storage and handling protocols. Maintained full documentation and compliance reporting.
  • All systems met survey requirements and compliance benchmarks
  • High standards achieved in electrical and mechanical works
  • Safe, controlled execution supported by effective isolation procedures
  • On-site efficiency enhanced through proactive issue resolution
  • Positive feedback from client on support, quality, and safety performance
Value Delivered

SeaReady’s integrated delivery and project management model ensured seamless coordination across multiple trades and services. With a single point of contact, clear communication, and a commitment to safety and compliance, the project was delivered on time and to specification, reinforcing our trusted partnership with Rio Tinto.